The obligation calendar ✅

EV charging compliance as code: AFIR, ISO 15118-20, LSV, PAngV, MessEG, THG-Quote, MiSpeL, § 14a, NIS2, CRA — dated, cited duties per charge point and company.

The obligation calendar in emob-core answers “is this charge point, provider or company compliant on this date?” — duty by duty, each with its legal citation, the date it starts to bind, and a remedy. European charging regulation (AFIR, the EU Alternative Fuels Infrastructure Regulation, plus German and cybersecurity law) arrives in stages between 2024 and 2028, binds different subjects, and has explicit exemptions, so readiness is a query rather than a document.

use emob_core::obligation::assess;
use time::macros::date;

let report = assess(&point, date!(2027-01-01));

for finding in report.breaches() {
    println!("{}  {}", finding.obligation.citation, finding.obligation.remedy);
}

Three subjects: charge point, provider, company

flowchart TB
    CAL["the calendar<br/>51 dated, cited duties"]
    CAL -->|"assess"| P["charge point<br/>power · access · dates · payment"]
    CAL -->|"assess_provider"| M["mobility service provider<br/>disclosure · roaming surcharge"]
    CAL -->|"assess_undertaking"| U["the undertaking<br/>size · governance · incident reporting"]

    classDef one fill:#b8410f22,stroke:#b8410f
    class CAL one

Some duties bind the charge point, some the mobility service provider (the company selling charging to drivers), and some the undertaking — the company as a whole. A test asserts every duty is answered by exactly one of the three, so no duty can silently go unassessed. A company whose every charge point is compliant can still be in breach as a provider, and again as an undertaking.

Every duty in the calendar

51 duties over three subjects. “Reads” says which facts decide whether the duty applies.

DutySourceFromReads
Ad-hoc charging without a contract[AFIR Art. 5(1)]13.04.2024public; a free point satisfies it outright
A payment instrument widely used in the Union[AFIR Art. 5(1)]13.04.2024public ∧ paid ∧ deployed ≥ 13.04.2024
…retrofit at ≥ 50 kW on TEN-T or a safe and secure parking area[AFIR Art. 5(1)]01.01.2027reaches points deployed before 13.04.2024
The right not to use automatic authentication[AFIR Art. 5(2)]13.04.2024public ∧ offers it
Prices must not discriminate between end users and providers, or between providers[AFIR Art. 5(3)]13.04.2024public; differentiation only if proportionate and objectively justified
At ≥ 50 kW the ad-hoc price is based on a price per kWh[AFIR Art. 5(4)]13.04.2024deployed ≥ 13.04.2024
At ≥ 50 kW the €/kWh and any occupancy fee shown at the station[AFIR Art. 5(4)]13.04.2024deployed ≥ 13.04.2024
Below 50 kW every component available, in the prescribed order[AFIR Art. 5(4)]13.04.2024no deployment-date limit
The Arbeitspreis (price per kWh) at or beside the point, by one of three named media[PAngV §14(2)]28.05.2022public ∧ paid ∧ an ad-hoc payment method is in use — at any power
…and, where a web-based system is used, through it before the session starts[PAngV §14(2)]28.05.2022a second duty, not a fourth medium
…and every further price completely, in immediate vicinity[PAngV §14(3)]28.05.2022arises only where such a price is charged
The interface Annex II names — AC ⇒ Type 2, DC ⇒ CCS Combo 2, “at least”[AFIR Art. 21(1)]13.04.2024public — read off the connector list; [DA-656] replaced points 1.1–1.4 and excepts two bands at 3.7 kW
Provider: disclose every component, e-roaming costs included[AFIR Art. 5(5)]13.04.2024the provider profile
Provider: no extra charge for cross-border e-roaming[AFIR Art. 5(5)]13.04.2024the provider profile
Every public point is a digitally-connected recharging point[AFIR Art. 5(7)]14.10.2024public
Smart-recharging capable[AFIR Art. 5(8)]13.04.2024built after 13.04.2024 ∨ renovated after 14.10.2024
Fixed cable on every public DC point[AFIR Art. 5(10)]14.04.2025public ∧ DC
A third-party owner must supply a point whose characteristics let the operator meet 5(2), (7), (8), (10)[AFIR Art. 5(11)]13.04.2024public ∧ the operator does not own it
Static data, including the 100%-renewable electricity indicator[AFIR Art. 20(2)(a)–(b)]14.04.2025public
Dynamic status, availability and ad-hoc price[AFIR Art. 20(2)(f)]14.04.2025all public points, including free charging
A free, unrestricted API registered with the NAP[AFIR Art. 20(3)]14.04.2025public
…the German feed in the DATEX II Recharging profile[DATEX-II-Profil]14.04.2026public
EN ISO 15118-1…-5[DA-656 Anh. 2.1.1]08.01.2026public ∧ installed or renovated ≥ 08.01.2026
EN ISO 15118-20, public[DA-656 Anh. 2.1.2]01.01.2027public ∧ installed or renovated ≥ 01.01.2027
EN ISO 15118-20, private Mode 3/4[DA-656 Anh. 2.1.3]01.01.2027private ∧ not Mode 2 ∧ installed or renovated ≥ 01.01.2027
Automatic authentication ⇒ both -2 and -20[DA-656 Anh. 2.1.2]01.01.2027AutoCharge counts, not only Plug & Charge
Every point meets the technical requirements (§ 49(1) EnWG)[LSV26 §3]01.01.2026public — the duty § 5(1)–(3) are exercised over
…and the operator can prove it on request[LSV26 §4]01.01.2026§ 4(2)
Commissioning notified within two weeks[LSV26 §4]01.01.2026§ 4(3) runs it from the day a point became public
Decommissioning notified unverzüglich (without undue delay)[LSV26 §4]01.01.2026§ 4(1) Nr. 2
An operator change notified by both operators[LSV26 §4]01.01.2026§ 4(1) S. 2 — one notice is not enough
Conformity-assessed meter for energy billing[MessEG §33]01.04.2019bills by energy
…on a meter whose verification period has not expired[MessEG §37(1)]01.04.2019bills by energy — eight years [MessEV Anl. 7 Nr. 6.7] from the placing on the market, ending with the calendar year [MessEV §34(2)]
…and every intervention on it recorded, firmware pushes included[MessEG §31(2)]01.04.2019bills by energy
A provider billing on somebody else’s meter owes a confirmation from its operator[MessEG §33(2)]01.04.2019the provider profile
Verifiable measured values[PTB-A 50.7]01.04.2019bills by energy
AC metering before the rectifier only in DC stations placed on the market before 2018 and at most 50 kW[REA 6-A]16.03.2017the same number as AFIR’s threshold, pointing the other way
…and only where the rectification belongs to one session[REA 6-A]16.03.2017a shared rectifier fails it
…and the customer must be told the rectification loss is inside the value[REA 6-A]16.03.2017see the Eichrecht chain
THG-Quote: publishable register entry, lawful metering, issued operator code[38k §6(3)]standingpublic
The undertaking gives the authority its details[NIS2 Art. 3(4)]06.03.2026an Annex I type of at least medium size; three months from coming into scope
…and takes all ten risk-management measures[NIS2 Art. 21(2)]06.12.2025a conjunction, not a score
…and can warn the CSIRT within 24 h[NIS2 Art. 23(4)]06.12.2025then 72 h, then a report within a month
The management body approves and oversees the measures[NIS2 Art. 20(1)]06.12.2025its members are liable
…and its members attend cybersecurity training[NIS2 Art. 20(2)]06.12.2025required for the body, encouraged for all staff
A manufacturer reports an exploited vulnerability within 24 h[CRA Art. 14]11.09.2026only where products with digital elements are placed on the market
…and places only conformity-assessed products on the market[CRA Art. 13]11.12.2027Annex I Part I ∧ Part II vulnerability handling
A § 14a device is always controllable[BK6-22-300 Ziff. 4.6]01.01.2024a non-public point over 4.2 kW, commissioned from that date
The grid operator’s reduction outranks market-driven load control[BK6-22-300 Ziff. 4.6]01.01.2024a non-public point over 4.2 kW, commissioned from that date
MiSpeL: fed-back energy is relieved of levies only under a Formelsatz with its metering concept[MiSpeL A1 3.2.5]21.10.2026bidirectional; an entitlement, not a duty
MiSpeL: until 30.09.2027 only with the grid and metering operators’ consent[MiSpeL Tenor 9]21.10.2026bidirectional; ends 30.09.2027; an entitlement

Six possible answers per duty

A private depot is not failing the ad-hoc payment duty — the duty does not bind it. So each duty has one of six statuses:

StatusMeaning
Satisfiedbinds this subject, and it is met
Failingbinds this subject, and it is not
NotApplicabledoes not bind this subject
NotYetInForcehas not started binding yet — plan for it
NoLongerInForcebound once, since superseded
DifferentScopebinds a different kind of subject

Every duty carries applies_from (and applies_until where superseded), and you can only use the calendar by asking about a date, so a duty is never applied before it exists:

// DATEX II starts on 14.04.2026.
assert_eq!(status_on(date!(2026-04-13)), Status::NotYetInForce);
assert_eq!(status_on(date!(2026-04-14)), Status::Failing);

Breaches versus a forgone entitlement

Three of the fifty-one entries are not duties. The four conditions for the greenhouse-gas quota (THG-Quote) are worth money but break no law when unmet, and so are the two MiSpeL entries: a bidirectional point without a Formelsatz (mispel-metering-concept, from 21.10.2026) or, until 30.09.2027, without the grid and metering operators’ consent (mispel-operator-consent) has broken nothing — it pays the levies on all of its grid draw. So each entry says what failing it costs, and the report separates them:

report.verdict();      // Compliant — nothing unlawful
report.breaches();     // what a regulator can act on
report.forgone();      // money left on the table, not a breach
report.failing();      // both, for a caller that wants the union

Exemptions that are easy to miss

Each of these is modelled as NotApplicable, not as a pass:

Every duty is tested in both directions

A property test checks the whole table: a subject that does everything asked fails nothing, and every entry fails for at least one subject in a panel (a bare point, a fast DC charger doing nothing, the same charger deployed before 13.04.2024, a private wall box from 2027, a provider, a surcharging provider, and an undertaking in NIS2 scope doing nothing). This catches a check that reads the wrong field and is therefore always satisfied.

Citations are checked at build time

cargo xtask check-citations finds every citation in code and docs and fails the build if one names a document the reference index does not list. The documents are third-party and not in the repository; the index records where to retrieve each.

Provider duties under AFIR Art. 5(5)

[AFIR Art. 5(5)] binds the mobility service provider, not the point: it must disclose every price component, e-roaming costs included, and may not surcharge cross-border roaming. It is judged against a ProviderProfile:

let mut provider = ProviderProfile::bare(PartyId::new("DE", "MSP")?);
provider.discloses_all_price_components = true;
provider.discloses_electronically = true;

// Still failing: the e-roaming cost is a component the article names explicitly.
assert_eq!(
    assess_provider(&provider, today).status_of(ObligationId::AfirMspPriceDisclosure),
    Some(Status::Failing),
);

provider.surcharges_cross_border_roaming = true; // forbidden outright
assert_eq!(assess_provider(&provider, today).verdict(), Verdict::Failing);

[AFIR Art. 5(6)] tells authorities to monitor operators and providers for compliance with paragraphs 3 and 5 specifically. Paragraph 5 is the provider duty above; paragraph 3 binds the operator — prices must be reasonable, comparable, transparent and non-discriminatory, and differentiation is allowed only if “proportionate and objectively justified”. Both are in the calendar. The comparability and transparency limbs are enforced through the display duties of Art. 5(4) and the tariff shape check.

[AFIR Art. 5(11)] binds neither: where a host (hotel, supermarket, municipality) owns the charger and a CPO operates it, the owner must supply hardware that lets the operator meet Art. 5(2), (7), (8) and (10). The remedy says the fix is a contract clause, not a technical change.

NIS2 and the Cyber Resilience Act: duties of the company

[NIS2 Anh. I] names charge point operators in the Energy sector. None of what it asks is a fact about a charge point — size, governance, incident reporting are facts about the undertaking:

let mut operator = UndertakingProfile::bare(PartyId::new("DE", "CPO")?);
operator.operates_recharging_points = true;
operator.employees = 400;
operator.risk_management = RiskManagement::complete();
operator.risk_management.supply_chain_security = false;

assert_eq!(operator.nis2_class(), Some(Nis2Class::Essential));
assert_eq!(operator.risk_management.missing(), vec!["(d) supply-chain security"]);
assert_eq!(
    assess_undertaking(&operator, today).status_of(ObligationId::Nis2RiskManagement),
    Some(Status::Failing),
);

Seven duties: five from NIS2 (registration, the ten risk-management measures, the 24-hour early warning, management approval, training) and two from the Cyber Resilience Act, which bind only a company that places products with digital elements on the market. The ten measures are a conjunction — the article says they “shall include at least” all ten.

Three details that are easy to get wrong, all tested:

The CRA is a Regulation, so [CRA Art. 71]’s dates apply directly in every Member State: 11.09.2026 for vulnerability reporting, 11.12.2027 for the rest.

This repository’s own CRA practice

emob is software with digital elements too, so the repository carries the artefacts the CRA’s vulnerability-handling duties ask of a manufacturer:

DutyHere
A disclosure routeSECURITY.md (GitHub private vulnerability reporting) and /.well-known/security.txt on this site
An SBOM per releaseone CycloneDX file for the workspace (just sbom), attached to every GitHub release
Provenancea build-provenance attestation over every .crate and the SBOM; images carry BuildKit provenance
Known advisoriesdecided in deny.toml with the exposure analysis and a review date, so cargo deny stays green

Which date AFIR means: deployed, built, installed or renovated

Article 5 uses three wordings, and they are not interchangeable:

WordingReadsDuties
“deployed from 13 April 2024”commissioned_on5(1), 5(4)¶1–2
“built after … or renovated after …”both, with different dates5(8)
“installed or renovated from …”installed_or_renovated_on()[DA-656 Anh. 2.1]

A renovation is not a deployment; reading it as one drags untouched 2019 hardware into duties written for new equipment:

point.commissioned_on = date!(2019-01-01);
point.renovated_on = Some(date!(2026-03-01));

// The card-reader duty binds points *deployed* from 13.04.2024. This one wasn't.
assert_eq!(status(ObligationId::AfirPaymentInstrument), Status::NotApplicable);

// Smart recharging says "renovated after 14 October 2024", so it binds.
assert_eq!(status(ObligationId::AfirSmartRecharging), Status::Failing);

Art. 5(4)’s date limit covers only its first two subparagraphs, so the ordered price components below 50 kW apply to the whole installed base.

ISO 15118 duties: the exemption is a date, not a technology

[DA-656] (Delegated Regulation (EU) 2025/656) exempts existing points by date: 2.1.1 binds points “installed or renovated from 8 January 2026”. Testing the technology as well (“not applicable if the point only does PWM”) would let a PWM-only point installed in 2026 escape the duty because it fails it.

// A PWM-only point installed in June 2026: failing.
assert_eq!(status(&fresh, ObligationId::Da656Iso15118Dash2), Status::Failing);
// A 2019 point: out of scope, by date.
assert_eq!(status(&legacy, ObligationId::Da656Iso15118Dash2), Status::NotApplicable);

The 2027 generation is three duties: 2.1.2 for public points, 2.1.3(b) for private Mode 3/4 points (a domestic socket with an in-cable box is Mode 2), and 2.1.2’s second sentence for automatic authentication — which includes AutoCharge, not only Plug & Charge.

ISO 15118-20 on 01.01.2027: where it stands (18.11.2026)

On the platform side, emob-pnc validates ISO 15118-20 contract chains under their own roots — see Plug & Charge.

E-invoices from 01.01.2027

From 01.01.2027 a German business whose prior-year turnover exceeds €800,000 must issue e-invoices to business customers: the structured EN 16931 file is the invoice [UStG §14(1)]. The Federal Ministry of Finance’s letter of 15.10.2026 (III C 5 - S 7287-a/00019/021/017) supplements its letters of 2024 and 2025 and postpones nothing. It is a capability of the platform, not a charge-point duty, so it has no calendar entry: billd issues each partner’s monthly invoice in EN 16931 or XRechnung, serves it on an invoice page with its UBL and CII files, and hands it to the operator’s ERP or Peppol provider through a signed CloudEvent — see Run the estate.

MiSpeL: levy relief for bidirectional points

The Bundesnetzagentur’s MiSpeL ruling, in effect from 21.10.2026, relieves of levies the part of a site’s grid draw that a bidirectional point fed back. The calendar carries its two preconditions as entitlements (above); emob_session::mispel does the arithmetic per calendar month (Abgrenzungsoption) or year (Pauschaloption). The Pauschaloption is refused until the European Commission approves it under state-aid law [MiSpeL Tenor 9], because the ruling makes it applicable only from the month after that approval. See Bidirectional charging and MiSpeL.

The Ladesäulenverordnung (LSV 2026)

The German charging-point ordinance lets the Bundesnetzagentur inspect, demand a retrofit for, and forbid the operation of a point [LSV26 §5]. It names AFIR Art. 5(1), (2), (7), (8) and (10); the last three are often missed:

[LSV26 §3] adds the duty those powers are exercised over: every public point meets the technical requirements of § 49(1) EnWG. [LSV26 §4] is four duties:

DutyTextThe trap
Commissioning notice§ 4(1) Nr. 1 — “spätestens zwei Wochen nach der Inbetriebnahme”§ 4(3) restarts the clock “wenn ein bestehender Ladepunkt öffentlich zugänglich wird” — a depot charger opened to the public owes its notice from that day
Decommissioning notice§ 4(1) Nr. 2 — “unverzüglich”a point still shown as live is one the operator still answers for
Operator-change notice§ 4(1) Nr. 3 and S. 2both the outgoing and incoming operator must notify
Evidence on request§ 4(2)being compliant and being able to prove it are separate duties

A deadline is a date compared to a date, not a flag:

point.commissioned_on = date!(2026-03-01);

point.registration = Registration::notified_on(date!(2026-03-22));
assert_eq!(status(ObligationId::Lsv2026CommissioningNotice), Status::Failing);

point.registration = Registration::notified_on(date!(2026-03-10));
assert_eq!(status(ObligationId::Lsv2026CommissioningNotice), Status::Satisfied);

Unverzüglich — “without culpable delay” [BGB §121] — has no number. The calendar uses the two weeks the same paragraph gives for commissioning, as a separate constant (Registration::PROMPT_NOTIFICATION_DAYS) so a deployment can see and change it; Notice::delay_days reports how late a filing was.

[LSV26 §6] also has the regulator forward notifications monthly to the state calibration authorities, so filing a § 4 notice puts the point in front of the Eichrecht regulator. It binds the regulator, not the operator, so it is not a calendar entry.

THG-Quote: the greenhouse-gas quota

[38k §6(3)] sets four cumulative conditions before a public charge point’s kilowatt-hours earn the quota. emob-thg’s QuotaPosture holds them in the paragraph’s order:

  1. The regulator has published the point, or the operator consented to publication — not merely that the § 4 notice was filed.
  2. The energy was measured in conformity with calibration law — emob-thg refuses a record with no evidence, and one whose evidence failed.
  3. The operator holds an identification code issued by a registration organisation [AFIR Art. 20(1)] — a well-formed EvseId is not proof.
  4. Further identifiers, only if announced in the Bundesanzeiger. None are today, so FurtherIdentifiers has three states rather than a boolean.

[38k §8(1)] sets the filing deadlines: 28 February of the following year for the § 6 route and 15 November of the obligation year for § 7. Route::deadline carries both. One notification per point per year is allowed [38k §8(1) S. 3], so adding a point twice is refused.

The § 7 route for vehicle fleets

[38k §6][38k §7]
claimantthe operator of the pointthe vehicle’s registered keeper
the quantitya measured value under calibration lawa published estimate, once per vehicle
the evidencea signed meter recorda registration certificate (Zulassungsbescheinigung Teil I)
the deadline28 February of the following year15 November inside the obligation year
the counting factor[38k §5(3)][38k §7(6)] — M3/N3 reach 4

[38k §7(6)] gives buses and heavy goods vehicles (classes M3 and N3) a factor of 4 from 2027, stepping down 3.5 (2035), 3 (2036), 2.5 (2037), 2 (2038), 1.5 (2039), 1 (2040) — a third more than § 5(3)’s 3. That matters for depot operators, whose non-public posts are excluded from § 6 but whose own buses count under § 7. A vehicle counts once per year [38k §7(4) S. 2], keyed by an identifier unique within the filer’s records, never a licence plate.

§ 14a EnWG: controllable charge points

[EnWG §14a] lets a grid operator reduce the draw of steuerbare Verbrauchseinrichtungen (controllable devices), and [BK6-22-300 Ziff. 2.4.1] defines them to include a charge point over 4.2 kW in low voltage

der kein öffentlich zugänglicher Ladepunkt im Sinne des § 2 Nr. 5 der Ladesäulenverordnung (LSV) ist

— so a publicly accessible point is outside § 14a; depots, workplace car parks and fleet yards are inside it. Charge points count one by one, because Ziff. 2.4.2’s grouping applies only to heat pumps and space cooling.

The two duties in the table — always controllable, and the grid operator’s reduction outranking market-driven load control [BK6-22-300 Ziff. 4.6] — read grid.always_controllable and grid.grid_reduction_takes_priority. The second is the one a load manager gets wrong: obeying a setpoint until a dynamic tariff says otherwise is controllable and still in breach. emob-smart meets it by construction.

What the site may draw when the grid operator goes silent is set by EEBUS’s Limitation of Power Consumption use case [LPC §2.3.2]:

StateThe ceilingReported
initconfigured failsafe power—
limitedthe setpoint—
unlimited/controlledthe site’s connection—
failsafe state [LPC-912]the Failsafe Consumption Active Power Limit [LPC-021]yes
unlimited/autonomous [LPC-922]the site’s connectionyes
no control box commissionedthe site’s connection—

GridLimit models the five protocol states and a site with no commissioned guard. The guaranteed minimum power of Ziff. 4.5 holds under failsafe too. Applicability lives in emob-core; the power arithmetic is in emob-smart — see § 14a and the grid.

Planning ahead and sweeping an estate

// What lands on the fleet between now and the end of 2027?
for o in starting_between(date!(2026-09-01), date!(2027-12-31)) {
    println!("{}  {}  {}", o.applies_from, o.citation, o.title);
}

agentd’s compliance specialist runs this over a whole estate: every point against every duty, grouped by duty (four hundred posts without a CSMS connection is one firmware programme, not four hundred findings), and every upcoming duty judged at its own start date against the estate as it stands. A point due for renovation in March 2027 that speaks only ISO 15118-2 is compliant today and is flagged now as a breach from the day it is renovated. The date is an argument, so a run replays to the same answer. The specialist runs in the agentd daemon under the read-only advisory principal; ⏳ nothing in the estate triggers a run.

Limits